Ade appeared on Wednesday morning with the aim of removing Caliban’s well-worn smokebox by the end of the day. Space is at a premium in the FRT shed but Ade managed to appear with a fork lift truck and the weltrol on which the boiler is mounted was shunted into position by pinch bar. At this point additional hands were summoned and, with assistance from Paul Balshaw, John Dixon and Ron Crowe, the job was done in time for elevenses to be taken!
John Davis took up the job of cleaning up a heater guard from the west saloon of Great Eastern Railway Royal Saloon No. 5. It was only after he had applied some wire wool to it that it was revealed that the guard was made of brass which looked very regal once old paint and dirt had been removed and a little Brasso applied.
Giving it a daily polish will be just another job for the train guard to do to keep the coach spick and span! And John now only has another couple of heater guards needing similar treatment! Of particular interest was last night’s Channel 5 programme on Queen Consort Alexandra for whom, at the time she was Princes of Wales in 1898, the coach was built. She seems to have been quite a character and the programme is worth a watch on MY 5 if you can spare the time. Here is a link to the programme.
We mentioned last week that Keith has mounted the ejector exhaust pipe on GWR ‘Hall’ class No. 4979 Wootton Hall, so here is the promised photo.
And the safety valve bonnet is also now in place.
Furness Railway No. 20 is due its 14-month boiler inspection shortly so Sam has been busy cleaning the firebox and smokebox. A boiler washout is planned or Friday when, hopefully, we will again hear the roar of the Coventry Climax fire pump.
We better not make this blog too long as Neil has to take the notes at this evening’s Trustees’ Meeting. Unfortunately, it will again be by Zoom so we will still be on virtual sandwiches (cue howls of dismay from Trustees missing Alison’s sarnies!).
We start with Peckett 0-4-0ST Caliban where the last tubes were
Once more there has been much work on Great Eastern Railway Royal Saloon
Meanwhile, John Dixon has been repairing one of the brass window supports
Finally, Alison kindly left us some of her tasty butterfly cakes on Wednesday, which were the left-overs from the RSR AGM the previous evening, where Ade had done his best to eat them! Needless to say, there were none left when Alison popped in to enquire on Friday lunchtime!!!
Work has continued apace on Great Eastern Railway Royal Saloon No. 5. Anne and Phil Burton are making progress on the chaise longue in the east saloon where repairs to the wooden frame have been necessary.
John Dixon, seen here painting a lamp bracket, has just about completed painting the components on the exterior of the coach in a specially mixed shade of brown.
Ed has continued to remove old paint and varnish from the guard’s compartment.
John Davis has been giving his attention to sprucing up the Royal toilet roll holder!
Tim has been giving the interior woodwork a couple of coats of varnish. Once dried, the new fabric is fitted to the lower panels. Phil has been in charge of the scissors.
It’s a two-handed job to fit the fabric, with John Davis lending a hand here.
Elsewhere, Fred has started to prepare Caliban’s boiler for an NDT inspection, cleaning off old rust and dirt.
Finally, the new screw for Wootton Hall’s reverser has now arrived, seen here on top of the fabricated reverser body. This opens up further work on this mechanism.
Talking of dates for your diary, Alison has arranged for this year’s FRT Christmas Dinner to be held at The Ribble Pilot pub on Preston’s dockside on the evening of Friday, 16th December.
We have also seen further progress on the overhaul of Great Eastern Railway Royal Saloon No. 5 where John Dixon has been replacing grab handles, lamp holders and the like to the exterior of the vehicle.
The fabric to line the interior sides of the coach has arrived and Phil Bell is seen here cutting some white backing sheets.
And here is the first panel to be fitted with the new fabric, with shiny varnished woodwork above, and a sneak preview of what the whole coach will look like when completed.
We are however pleased to report that the working party at Bury last Monday was successful in removing most of the items from 5643’s smokebox in order for a full hydraulic test of the locomotive to take place on Friday. Keith also went across to Bury on Tuesday and Thursday to complete the job and apply the necessary blanks. Even better, the locomotive passed its test in front of the boiler surveyor and so a steam test has been scheduled for this coming Friday. This will require a further working party tomorrow, Tuesday, to reassemble the items in the smokebox. Unfortunately, the hostile environment of the smokebox had eaten away at the ejector exhaust pipe and so it came out in two pieces rather than one. Keith has since been busy at Preston cleaning up and annealing the pipework.
He has also made up a new pipe for the ejector.
The first layer of varnish has been applied to the woodwork in the west saloon of Great Eastern Railway royal saloon No. 5 and also one side of the interior doors. The two doors on the right have received the varnish and those on the left await their turn. The end result looks good and is due reward for the all the effort that has been made to strip off previous layers of varnish. Work has also been going on behind the scenes by Andy Allthorn to produce replacement light fittings and obtain new glass bowls which will hopefully be arriving at Preston shortly along with the new LED light bulbs which have been procured.
Finally, those of you who attend working parties at Preston will be aware of the football rivalry within the FRT shed between Preston North End and Blackpool fans. The 4-2 home win by Blackpool the previous Saturday prompted Ed to turn up in his dayglo tangerine football shirt, much to the dismay of PNE supporters Phil Burton and John Davis!
Ade and Alan made some good progress in removing the last of Caliban’s tubes from its boiler last Wednesday. Ade worked in the firebox to “encourage” each tube to move forward.
Ade then joined Alan in hauling the tube out through the front tube plate. Inevitably some tubes were more reluctant than others to move!
David Starkie made a welcome return to work last Wednesday after convalescence and is seen here on the right assisting Ed (left) and Phil Burton (middle) on repairs to the chaise longue in Great Eastern Railway Royal Saloon No. 5. Varnishing of the exterior of the vehicle is now complete and all the brass work has been re-fitted. Phil Bell has repaired most of the interior mouldings and John Davis has been cleaning down woodwork in the west saloon ready for varnishing.
Most of the interior mouldings are now back in place and repaired by Phil. John and Ed meanwhile continue to clean up the woodwork, John on hands and knees in the former royal lavatory (a posture which somehow feels appropriate?!) and Ed in the kitchen. A short planning meeting took place last Wednesday with Alison to determine the future catering requirements and fitments required to bring the kitchen are up to modern standards. A preference for the remainder of the internal fabric decoration has also been determined – needless to say, it was the most expensive in the catalogue. Another round of measuring is required to ensure that we do not over order!
John Dixon has been fastidiously re-fitting the highly polished door knobs and handles, adjusting where necessary to ensure correct functioning of the door locks.
Sam has continued his work to re-install the lighting in the coach, seen here wiring up the light fittings.
Work has continued to progress well on the overhaul of Great Eastern Railway Royal Saloon No. 5. Having received the moquette for the chaise longue, it is now time to choose the rest of the material that will adorn the inside of the saloons and corridor below the windows. The first of the fabric samples have been received and examined. Naturally, the current preferred choice seems to be the most expensive! Meanwhile, Tim has been applying the final coat of vanish to the exterior of the vehicle.
There will soon be a need to re-fit the exterior fittings so John Dixon and Fred set about cleaning and polishing the door knobs and handles on Friday.
Work has also continued on Wootton Hall where Keith has been removing some very stubborn brackets from the insides of the engine’s frames. John Dixon has also been continuing his Saturday job of repairing Caliban’s cab.
The weekend saw the operation of Ribble Steam Railway’s very successful Steam Gala which featured five steam locomotives including Furness Railway No. 20 and visiting L&Y ‘Pug’ No. 19.
The latter will depart Preston on Wednesday after its month-long stay at the RSR.
However, there has been plenty going on at Preston where the team working on Great Eastern Railway Royal Saloon No. 5 is finally beginning to see the light at the end of the proverbial tunnel. John Dixon is seen here replacing one of the ceiling vents that he has been fettling and polishing.
The new moquette for the chaise longue has arrived after a delay and now will enable us to search for a suitable shade of matching material for the lower side panels in the saloon.
Anne and Phil have been stripping down the chaise longue ready for new materials to be fitted.
Phil has been applying a first coat of varnish to the new veneer panels.
John Davis and Ed continue to clean up the remaining woodwork; it’s John’s turn for a photo this week.
Inevitably during this restoration we have discovered missing components that will be difficult to replace. However, we were visited on Wednesday, 14th, by 3D printing expert Andy Allthorn from Cark-in-Cartmel who kindly came down to demonstrate how this modern technology can used in re-creating such items and has already produced a new part for the light fittings.
Andy has also now set about re-creating handles for two of the internal sliding doors.
Dave Watkins has been able to supply a replacement cast brass oil box (no 3D printing here) for Wootton Hall’s tender which Keith has been working on.
Fred has been polishing one of the trunnions for a brake shaft for Wootton Hall.
Bob has been visiting regularly to work on Wootton Hall‘s regulator valve.
Alan and Sam have taken Caliban’s piston rods to Burscough for them to be metal spayed and ground in order to repair corrosion.
This last Saturday saw the Furness Railway Trust shed open to the public as part of the national Heritage Open Days scheme. We were delighted to welcome so many visitors and Tim admitted to having to keep up his tea uptake in order to avoid a dry throat during his many guided tours around the shed. The work on restoring GWR ‘Hall’ class 4-6-0 Wootton Hall and the overhaul of Great Eastern Railway Royal Saloon No. 5 proved to be of particular interest and it is to be hoped that some of the visitors will become members to support this work. Outside the shed Ade was driving recently restored Lancashire & Yorkshire Railway ‘Pug’ 0-4-0ST No. 19 of 1910, courtesy of the L&Y Trust. At the other end of the trains was the FRT’s very own Furness Railway No. 20 with Alan and Sam Middleton on the footplate – not often you get locomotives with sequential numbers powering a train!