Just a very brief Bank Holiday update for you.
More work was carried out on FR 20’s engine frames, including the chipping away of loose concrete on the cylinder block by Phil Scales.
Alan spent some more time investigating Cumbria‘s left hand clackbox to try and eliminate any showing of steam at the injector tail pipe. It is proposed on Wednesday to re-pack the left hand piston gland, which started to blow over the RSR’s Steam Gala, before conducting another steam test. It is expected that Cumbria will be then heading off to Embsay shortly to join the FRT’s 0-6-2T 5643 for the season.
Ade and Mike set about moving 0-4-0DM Fluff last Wednesday afternoon in order to position it over the pit. Stanlow was brought around from the running shed and, after a complicated set of moves, Caliban‘s boiler was moved out of the shed and then Fluff took its place.
This should enable the engine to be lifted for overhaul.
As ever, Keith has been busy with Wootton Hall and is seen here measuring up the cab.
We must mention the sad news that Fylde based folk singer, Alan Bell, passed away a week last Thursday at the age of 84. Alan wrote many fine songs, including the much-covered “Bread and Fishes”, and was Director of the long running Fylde Folk Festival, to which the FRT supplied sound personnel and equipment for 17 years, which in turn helped the Trust’s coffers. Alan’s funeral is at Carlton crematorium at 10.30 this Friday.
Finally we cannot go without resolving the mystery photo from 7 days ago!
Mike Rigg’s shot was taken through one of the holes made in Caliban‘s buffer beam to enable the cylinders to be re-bored.
Ade got himself out of bed at an early hour to light up Cumbria (thank you, Ade) so that it could undergo a pre-hire inspection in steam by Tony Wright of the Embsay & Bolton Abbey Steam Railway. All went well and Cumbria then went on to appear at the RSR’s Spring Steam Gala on Saturday and Sunday. It is seen here being prepared on Sunday morning and also at the head of the 11.30 train from Riverside station on Saturday with Hudswell Clarke 0-6-0ST No. 1208 Illingworth (also bound for Embsay in the near future) on the rear.
John Dixon has been measuring up one of Wootton Hall‘s tender axleboxes so that he can make a pattern for a casting to repair some damage.
John Davis has been spending more time working on Wootton Hall‘s new tender tank.
Tim has again been cleaning up FR 20’s frames whilst Roger Benbow set to work on cleaning up the crinolines for FR 20’s boiler.
Work has also continued on Fowler 0-4-0DM Fluff where a replacement running board support, fabricated by John Stewart, has been fitted.
Over at Embsay, 5643 has been busy turning its wheels again and we have an Instagram photo here of it on a dining train there.
Also, Mike Rigg has submitted a mystery photo for you identify. Answer next week.
Work at Preston last Wednesday concentrated on following up issues brought to light from the test steaming of Cumbria two days earlier. Alan is seen here peering into the fireman’s side clackbox to try and identify the cause of a small steam pass.
Finally, outside the shed, work has continued on cleaning off and painting of Wootton Hall‘s recently purchased tender tank. In action on this are Phil Scales and John Davis (above) and Ed Tatham (below).
The Trust’s ‘Austerity’ 0-6-0ST Cumbria was once again the centre of attention this last week as final preparations were made for a test steaming. The loco had a second washout on Wednesday and the mudhole doors and washout plugs were refitted. Alan finished fitting the regulator quadrant and John Dixon is seen here fitting the driver’s side water valve.
Phil Scales and Phil Bell continued the task of sprucing up the appearance of the loco with the latter touching up the black paint on the nameplates.
Ade appeared bright and early this morning and had Cumbria lit up by 8.15. Steam was raised just after 1.oo and the pressure brought up slowly. Tim and Matt Jervis were looking at the drain cocks closely with fingers crossed as steam built up, to detect whether the regulator or ‘J’ pipe were passing steam, but all was well. The afternoon was spent chasing up steam leaks on cab fittings and then moving the loco to test the regulator and brakes.
Tim is seen here tightening up the brake steam pipe to the manifold whilst Alan looks on.
A notable arrival this week has a package with the castings for Wootton Hall’s gauge frame.
Finally, when Tim went to the NRM at Shildon on Saturday for a training day, he came across an upstand advert inviting volunteers to work with the NRM’s historic collection featuring none other than Alan – is he now officially part of the NRM’s historic collection, we wonder?!
The main centre of activity this week has once again been the Trust’s ‘Austerity’ 0-6-0ST Cumbria as members have expedited the completion of the remainder of the winter maintenance programme. The key event on Wednesday was the task of re-installing the ‘J’ pipe and regulator valves. The photo shows John and Ade in the process of pushing the extremely heavy ‘J’ pipe rung by rung up a ladder whilst Phil Bell hauls on the safety rope to prevent it from dropping back down the ladder. It was a little unconventional, but was deemed to be the safest method – and what’s more, it worked. Matt Jervis was on top of the saddle tank to receive the ‘J’ pipe and secure it back on to the main steam pipe. By the end of Wednesday all was ready for the dome cover to be re-fitted, which was achieved on Friday.
Alan tackled the job of re-fitting the regulator stuffing box on Friday and John Dixon had completed the servicing of the water valves. Phil Bell and Roger re-fitted the balance pipe after a through clean.
The last job on Friday was the completion by Tim of the fresh coat of black paint on the running board and cab steps that had been started on Wednesday by both Phils.
Russ Walker kindly offered to arrange the movement of Cumbria around to the running shed on Saturday morning so that a further wash-out can be carried out this week, the plugs and mudhole doors be re-inserted, and (hopefully) a fire lit. It will be a case of fingers crossed as we check out the results of everyone’s labours over the past three months.
Cumbria has been replaced in the shed by Caliban‘s boiler, which can be seen here with FR 20’s boiler in the background.
Work has, as ever, continued on Fluff, the former L&NWR platform bench seat, and Wootton Hall‘s tender tank, which has now received a fresh coat of undercoat green on the first side to be cleaned off.
Bryn Engineering started the re-bore of Caliban‘s cylinders last Tuesday and continued into Wednesday. There is still some work to be completed which will be done shortly.
Again, the brake valve should be re-mounted this next week.
The running board and cab steps have received a coat of grey undercoat paint, courtesy of Phil Bell (pictured) and Roger.
Finally, over at the Embsay & Bolton Abbey Steam Railway, 5643 was, as planned, in steam for Mother’s Day.
Back at Preston, it has very much been a case of ‘more of the same’ as our members have continued to clean up the Trust’s ‘Austerity’ 0-6-0ST Cumbria. The running plate and cab steps have been rubbed down and primed ready for the undercoat to be applied this week.
New member Phil Scales is seen here busy with the sand paper.
Saturday and Sunday marked the start of 2019 passenger services on the Ribble Steam Railway with a successful Diesel Gala. Guest Colas C0-C0 locomotive No. 56 090 is seen here on the end of one of the trains.
Bob is seen applying his feeler gauge to check test progress. By the end of Friday both the regulator valve and the ‘J’ pipe were deemed to be in much better shape although further work will be required this next week. In view of time pressures, Tim spent another day on the job today.
The spruce up of Cumbria has also continued apace, led by John Dixon and assisted by Phil Bell and Phil Scales. The running board is receiving a rub down with a view to giving it a fresh coat of black paint in the near future.
Alan is seen here on Friday inspecting the results of Ade’s endeavours.
Roger spent more time cleaning, in this case up FR 20’s drawhook spring.
Bill Norcross has started the machining of the new axlebox brasses and completed the first successful fitting into an axlebox on Friday.
A great deal of progress was made on both Wednesday and Friday with the thorough clean being given to Cumbria. Roger, Phil Bell, and John Dixon have concentrated their efforts on the frames, motion and brake rigging whilst John Davis worked on the wheels.
Matt Jervis had successfully removed the ‘J’ pipe from the boiler which was subsequently machined by Bill Norcross.
Bob and Tim spent all their time on Friday (strictly limited number of tea breaks!) in their efforts to produce flat polished surfaces on both the regulator valve and ‘J’ pipe faces. Keith had kindly manufactured a flat steel plate to size with which to apply the carborundum paste although one or two high spots on the cast iron ‘J’ pipe needed some rather more aggressive attention! The task is still quite a way from completion and more work is planned for this next week.
A major project completed has been the installation of the new overhead safety wire system on road three of both the heated and unheated sections of the FRT shed. Wednesday, 20th February was spent on moving various pieces of equipment out of the way and taking delivery of a cherry picker and tower scaffold for use of the installers. That didn’t stop Adrian getting a few instructions on how to operate the cherry picker in order that it could be stowed away safely overnight.
Fortunately, despite a short power outage, work progressed steadily during the day.
With the rolling stock now out of the way, the opportunity was also taken to undertake a thorough clean of the central section of the shed including the pit.
Mike Rigg volunteered to try on one of the new harnesses and is seen here getting rigged up (geddit?!) with the assistance of Joe Jackson from Trad Safety Systems.
A rear view of Mike shows the correct position, between the shoulder blades, for the metal loop to which the back strap should be attached. The installers finished a little later than planned, but all the rolling stock was back in the shed by 17.30 and Stanlow moved back home to the main running shed. A full operating instruction for the overhead safety wire system has been written and is available both in the mess room and in the harness storage drawer in the shed filing cabinet.
One side benefit from the upheaval in the shed was the opportunity to re-marshal the rolling stock so that Cumbria and FR 20 could be positioned over the pit to assist maintenance and repairs.
Outside, Keith has been busy on repairs to the newly acquired tender tank for Wootton Hall and also in cutting up the original which, unfortunately, was well past being repaired. Alan has been loosening nuts with a view to removing FR 20’s valve chest cover and Adrian has been undercoating Caliban‘s frames. Work on Fluff progresses as well.